Plan the right test
Confirm route, operator, RAT, direction, test case, access, vehicle, people, timing, and the latest customer-approved scope.
An intern-ready operating guide for moving from a tentative plan to a safe field run, complete logs, actionable analysis, and a customer-ready report.
Core tools: PHU · PHU Assistant Lite · OsmAnd · Tracklia
KMZ route preview
Start: 21.0180095, 105.8296793
End: 21.0161248, 105.8321694
This page consolidates a project handover dated 1 September 2026. Group IDs, account IDs, test identifiers, routes, and issue counts are historical operational references. Verify them in WeLink before acting, follow Huawei and MobiFone information-security rules, and never forward logs, customer data, access photos, credentials, or restricted-site details outside approved channels.
A drive test is complete only when the route is covered, the requested test cases are valid, the raw evidence is safe, the team can find it, and the report explains what should happen next.
Confirm route, operator, RAT, direction, test case, access, vehicle, people, timing, and the latest customer-approved scope.
Maintain GPS lock and continuous logging; capture RSRP, SINR, PCI, throughput, events, BasicInfo, screenshots, and trace IDs where required.
Upload promptly, state incomplete items visibly, request analysis, include root cause and optimization suggestions, and track every dependency to confirmation.
A mobile field measurement along a planned road or indoor route.
A moving test that follows a route or floor map while the logger records continuously.
A fixed-point campaign covering accessibility, retainability, coverage, RxQual, one-way audio/crosstalk, and voice quality.
A voice-quality KPI, usually 1–5. The handover treats ≥3.0 as acceptable and ≥4.0 as good; always follow the current customer threshold.
File-transfer tests used to measure user-plane speed and stability.
A primary LTE/NR coverage-strength KPI.
A quality KPI that helps distinguish weak coverage from interference.
Identifies the serving or detected cell and helps reveal handover, overlap, and pollution behavior.
The indoor coverage layer; compare IBC serving behavior with outdoor macro coverage.
Capture LTE and NR serving-cell details at the same place and time as a static or speed test.
A trace used when deeper analysis is required; record the trace ID and exact test window.
PHU collects the field evidence, PHU Assistant Lite checks the logs, and OsmAnd or Tracklia keeps the team on the approved route. A navigation app never replaces the drive-test logger.
Use the approved Huawei PHU project and task to run the assigned LTE/NR, FTP, idle, voice, or mobility test and record the radio/GPS log.
Open the PHU log after the run to check route continuity, events, RSRP, SINR, PCI, throughput, test status, and whether the file is suitable for upload and reporting.
Correct product spelling; sometimes written “OmsAnd” in team messages.
Import the project KML/KMZ, which OsmAnd converts to a GPX track, download the Hanoi offline map, and use Follow track so the driver can see the approved path without depending on mobile data.
Use Tracklia on Android to import, inspect, combine, or carefully edit GPX/KML/KMZ tracks and waypoints. It is especially useful when a supplied path needs checking before field execution.
Open and verify in OsmAnd or Tracklia.
Collect the assigned test in PHU.
Inspect the result in PHU Assistant Lite.
Back up, upload, analyze, and report.
PHU and PHU Assistant Lite are project-controlled Huawei tools. Screens, task names, permissions, and menus vary by build; use the current project APK/license/profile and the team’s approved SOP.
This replaces the repeated workflow and checklist sections. Run it top to bottom for benchmark routes, walk tests, store tests, and VIP complaint verification.
28 Aug snapshot: two VNPT data + two voice SIMs; two Viettel data + two voice SIMs; MobiFone SIMs available at stores. Reconfirm current inventory.
Wrong SIM/task, no GPS, broken PHU logging, unknown RAT lock, expired access, unsafe traffic, missing permission, or an unapproved route change are stop conditions.
Use the same discipline—exact location, known configuration, synchronized evidence, and repeatable naming—while adapting the movement pattern and KPI focus.
KML/floor map, trace, direction, start/end time, deviations, public/restricted coverage.
Operator, RAT, band/lock, RSRP, SINR, PCI, throughput, latency, drops, MOS, BasicInfo.
UE/SIM mapping, test-case name, raw log, screenshot, VUE trace ID, event notes, valid-trial marker.
The 29–31 August benchmark compared Viettel, MobiFone, and Vinaphone across LTE/NR FTP UL/DL. MOS remained incomplete because voice-test SIMs malfunctioned.
| Route | Description | FTP status | Operational note |
|---|---|---|---|
| 1 | MobiFone Office → Government Office | Completed | FTP UL/DL completed; MOS pending in the 29–31 Aug run. |
| 2 | MobiFone Office → MPS Branch Office | Completed | Also recorded as a pre-FTPDL benchmark on 30 Aug. |
| 3 | MobiFone Office → MPS HQ | Completed | The handover history also records Route 3 to Government Office; verify the latest route master before departure. |
| 4 | MPS Branch Office → MPS HQ | Completed | Pre-FTPDL benchmark recorded on 30 Aug. |
| 5 | MPS Branch Office → Government Office | Completed | Pre-FTPDL benchmark recorded on 30 Aug. |
| 6 | MobiFone Office → Northern MobiFone Network Center | Completed | Separate pre-FTPDL and pre-FTPUL runs recorded on 30 Aug. |
| 7 | MPS HQ → Government Office | Completed | Separate FTP DL and FTP UL runs recorded on 31 Aug. |
| 8 | MPS HQ → Vinhomes Riverside | Retest | FTP UL completed; FTP DL blocked by low Viettel 4G / VNPT 4G balance. |
| 9 | MPS HQ → National Data Center | Completed | Longest route: about 2.5 hours; consider splitting the segment or reducing test scope. |
Before leaving the endpoint, mark every required combination—not just the route—as complete.
Use these examples to recognize common failure patterns: false 5G, macro cross-coverage, interference, access constraints, incomplete reporting, and missing resource follow-up.
Shop 1 improved after optimization. Shop 2 remained below the >10 Mbps UL target. A nearby VNPT antenna was about 12–15 m horizontally from the referenced building floor; the team requested interference and load checks.
Intern takeaway
Do multiple static trials, preserve comparison points, and do not call the problem solved when one location improves.
Indoor 5G was poor or absent while outdoor service was normal. One screenshot showed a 5G icon without a real NR connection.
Intern takeaway
Verify serving NR in BasicInfo. An icon is not proof of a 5G bearer. Compare indoor and outdoor under the same evidence package.
Indoor and outdoor 5G Speedtest plus FTP DL were collected at 21.0298, 105.8422 and combined with Ba La into one report.
Intern takeaway
Keep location identity and indoor/outdoor context clear when several stores share one deliverable.
Public areas on floors 1–3 were tested with 4G and 5G FTP DL. IBC improved, but some areas still handed over to macro. Restricted access had expired; Floor 3 public-area shape differed from the PPTX. 3G was not tested.
Intern takeaway
Report actual access and route coverage, state untested layers, and reconcile map mismatches before interpreting coverage.
Immediate DT required a local MobiFone staff member because interns could not enter the VIP area.
Intern takeaway
Access is a test dependency. Coordinate through Phan Tuan Anh and never attempt unapproved entry.
The report showed poor 4G/5G coverage but initially lacked analysis and optimization suggestions. The suspected root cause was severe cross-coverage; post-DT optimization was pending and relocation/transmission work was needed first.
Intern takeaway
A customer report needs cause, evidence, proposed action, dependency, owner, and next verification—not screenshots alone.
Most LTE/NR FTP UL/DL completed across three operators. Route 8 FTP DL failed because of low balance; all MOS tests failed because voice SIMs malfunctioned; Route 9 took about 2.5 hours and a missed turn added distance.
Intern takeaway
Test SIM balance and MOS function before departure, split long routes, brief the driver, and keep incomplete cells visibly red with a reason.
The source notes use a fixed six-block email structure, an operator-by-RAT status table, explicit failure colors, and a report template aligned before customer output.
State whether this is a plan, result, or update. For plans: “This is just a plan (tentative) and may change.”
Explain route, timing, access, SIM, vehicle, or scope changes before the table.
Use No. · Route · Operator · RAT · Test case · Status · Remarks. Expand every route by operator and LTE/NR.
Attach or CID-inline route maps, floor plans, BasicInfo, and screenshots with clear captions.
List driver, testers, field partner, start/end time, and access contact when relevant.
State the one core request, owner, deadline, disclaimer, and fixed signature.
Result email pattern
Subject: VIP 9 Road Benchmark Drive Test Result (29–31 Aug) – Viettel / MobiFone / Vinaphone
Opening: Please find below the benchmark drive test result for VIP 9 Road conducted from 29 to 31 Aug 2026, covering three operators: Viettel, MobiFone and Vinaphone.
Action wording: Route 8 FTP DL could not be completed because the Viettel 4G and VNPT 4G SIM cards had insufficient balance. New SIM cards have been requested; arrange the retest when availability is confirmed.
Rule: The table carries the complete facts. The body carries the conclusion, risk, and one actionable request.
Use role-based escalation first, then confirm the current person and account in WeLink. Never assume a historical contact still owns the task.
936714420879622473
Main coordination group for all drive-test activity.
997212977222389807
Noi Bai Airport T2 shop testing.
994063112594419792
Airport T1 assurance and MobiFone store testing.
Group Space > DT Management > North > Benchmark DT Log > [date] > [location]Open the handover Onebox location | Name | Account | Role | Use this contact for |
|---|---|---|---|
| Miao Peiqian | m00907087 | RF Delivery Leader | Direct leader for DT tasks; interference, load, and RF follow-up. |
| Ouyang Changjun | o60125604 | Delivery Leader | Overall delivery, VIP complaints, MobiFone coordination, and SIM purchase arrangement. |
| Hoang Minh Thao | h00708566 | Local MobiFone RF | Approves DT plans and reviews reports before customer delivery. |
| Phan Tuan Anh | p60120025 | Local engineer | Coordinates MobiFone/VIP access and tracks cross-feeder updates. |
| Su Xiaobo | s00921749 | GSC engineer | Performs log analysis and report writing. |
| Nguyen Ha Phan | n50066043 | Local engineer | Field-testing partner. |
| Phan Truong Khang | p50065883 | Local engineer | Field-testing partner. |
| Luo Yanyang | l00947656 | RF engineer | VIP complaint testing and Riverside DT support. |
ITC cross-feeder
64 issued · 40 resolved · historical counts do not fully reconcile; confirm current tracker.
MobiFone-S cross-feeder
75 issued · 66 resolved.
ITC hardware
93 issued · 36 resolved.
MobiFone-S hardware
51 issued · 27 resolved.
The handover totals 104 pending items. Phan Tuan Anh supplied ongoing updates.
CQT report retest
Installation-quality issues require a retest.
VIP residential analysis
Add optimization suggestions and address relocation/transmission dependencies.
Shop 2 uplink
Interference and load check requested; target was >10 Mbps.
Route 8 FTP DL
Wait for confirmed Viettel/VNPT SIM balance.
MOS for routes 1–9
Replace or repair voice/MOS SIMs, then complete all operators.
Phan Tuan Anh · send access documents only through approved channels.
Nguyen Trong Giap · 00079600; also check [War Room] MBF 5G project – Ha Noi cutover.
Ouyang Changjun coordinates with Dang Hong Quan / Thai Huu Tuan Ha.
Miao Peiqian for RF checks; Su Xiaobo for log analysis.
Use the live team workspace as the operational source of truth. These files are the dated references used to build this guide.
Before you leave for the field