Hovah Yii
RAN field playbook
Huawei × MobiFone Vietnam · Hanoi · 2026

Hanoi drive test field guide

An intern-ready operating guide for moving from a tentative plan to a safe field run, complete logs, actionable analysis, and a customer-ready report.

Core tools: PHU · PHU Assistant Lite · OsmAnd · Tracklia

VIP benchmark routes
9
Operators compared
3
LTE and NR
4G + 5G
Core test scope
UL · DL · MOS

KMZ route preview

“test path 1” · 14 points

STARTEND

Start: 21.0180095, 105.8296793

End: 21.0161248, 105.8321694

Browse this guide

Authorized project use

This page consolidates a project handover dated 1 September 2026. Group IDs, account IDs, test identifiers, routes, and issue counts are historical operational references. Verify them in WeLink before acting, follow Huawei and MobiFone information-security rules, and never forward logs, customer data, access photos, credentials, or restricted-site details outside approved channels.

01 · Mission and context

What an intern is expected to deliver

A drive test is complete only when the route is covered, the requested test cases are valid, the raw evidence is safe, the team can find it, and the report explains what should happen next.

Plan the right test

Confirm route, operator, RAT, direction, test case, access, vehicle, people, timing, and the latest customer-approved scope.

Collect trustworthy evidence

Maintain GPS lock and continuous logging; capture RSRP, SINR, PCI, throughput, events, BasicInfo, screenshots, and trace IDs where required.

Close the loop

Upload promptly, state incomplete items visibly, request analysis, include root cause and optimization suggestions, and track every dependency to confirmation.

Project scope captured in the handover

Project
MobiFone RAN 2026 · Vietnam · Hanoi / North
Handover scope
Drive-test work performed from August 2026 onward
Radio layers
LTE 4G and NR 5G
Core KPIs
RSRP, SINR, PCI, throughput, latency, call accessibility/retainability, and MOS
Log format
.gen.zip

Quick technical reference

DTDrive Test

A mobile field measurement along a planned road or indoor route.

CDTContinuous / walk drive test

A moving test that follows a route or floor map while the logger records continuously.

RSRPReference Signal Received Power

A primary LTE/NR coverage-strength KPI.

SINRSignal-to-Interference-plus-Noise Ratio

A quality KPI that helps distinguish weak coverage from interference.

PCIPhysical Cell ID

Identifies the serving or detected cell and helps reveal handover, overlap, and pollution behavior.

IBCIn-building coverage

The indoor coverage layer; compare IBC serving behavior with outdoor macro coverage.

BasicInfoRadio information screen

Capture LTE and NR serving-cell details at the same place and time as a static or speed test.

VUE TraceNetwork-side UE trace

A trace used when deeper analysis is required; record the trace ID and exact test window.

02 · Required tool stack

Know which tool owns each part of the job

PHU collects the field evidence, PHU Assistant Lite checks the logs, and OsmAnd or Tracklia keeps the team on the approved route. A navigation app never replaces the drive-test logger.

Primary field collection

PHU

Use the approved Huawei PHU project and task to run the assigned LTE/NR, FTP, idle, voice, or mobility test and record the radio/GPS log. Watch the task state and recording health throughout collection.

Post-test log verification

PHU Assistant Lite

Open the PHU log after the run to check route continuity, events, radio KPIs, service results, and invalid trials before upload. Preserve the untouched raw copy.

Offline route following

OsmAnd

Correct product spelling; sometimes written “OmsAnd” in team messages.

Import the approved KML/KMZ, download the Hanoi offline map, and use Follow track so the driver can follow the route without depending on mobile data. Never alter the original geometry without approval.

Route inspection and repair

Tracklia

Use Tracklia on Android to inspect GPX/KML/KMZ tracks and waypoints or prepare an approved corrected copy. It manages route data; it is not an RF logger.

PHU and PHU Assistant Lite are project-controlled Huawei tools. Screens, task names, permissions, and menus vary by build; use the current project APK/license/profile and the team’s approved SOP.

03 · Field runbook

One checklist, organized by field phase

Use this single phase-based checklist for benchmark routes, emergency-site tests, walk tests, store tests, and VIP complaint verification.

Before departure

  1. 1Confirm the latest route, operator × RAT × test-case matrix, direction, deadline, and report owner.
  2. 2Import the KML/KMZ into OsmAnd or Tracklia; verify start, end, direction, closures, and an alternate path.
  3. 3Secure restricted-area access, field partner, vehicle, driver, meeting point, and test window.
  4. 4Charge and label every phone; map each UE to its SIM, operator, RAT, and PHU task.
  5. 5Open PHU, sync the correct project/task, check GPS, storage, time, license, script, and log-size settings.
  6. 6Send the tentative plan and state that it may change.

During collection

  1. 1Run a short proof log, then confirm PHU is recording, GPS is stable, and the correct task is active.
  2. 2Follow the approved track in OsmAnd/Tracklia while watching PHU for gaps, crashes, heat, or storage errors.
  3. 3Record every deviation or anomaly with time, location, reason, impact, and retest need.
  4. 4Capture BasicInfo/screenshots at static points and repeat inconsistent trials two or three times.
  5. 5The driver drives; the tester operates the phones and logger.

Before close-out

  1. 1Before leaving, compare the PHU trace and task matrix with the planned route and confirm no log is truncated.
  2. 2Back up raw logs, then inspect them in PHU Assistant Lite for route continuity, KPI visibility, and valid trials.
  3. 3Upload to the approved dated folder, share the exact path, and identify incomplete or retest items.
  4. 4Notify analysis/report owners; include the issue, suspected cause, evidence, next action, owner, and due time.
  5. 5Recharge and hand over every phone, SIM, cable, power bank, and key.

SIM pre-flight

Correct operator
Enough balance/quota
4G/5G registers
VoLTE/MOS works
Correct phone/slot
Real traffic passes

28 Aug snapshot: two VNPT data + two voice SIMs; two Viettel data + two voice SIMs; MobiFone SIMs available at stores. Reconfirm current inventory.

Handover identifiers

Log format
.gen.zip
DT phone reference
841212953022
Recorded VUE trace
977718

Stop and escalate when validity or safety is at risk

Wrong SIM/task, no GPS, broken PHU logging, unknown RAT lock, expired access, unsafe traffic, missing permission, or an unapproved route change are stop conditions.

04 · Execution recipes

Benchmark, emergency-site, and field test recipes

Definitions and operating steps for FTP/MOS operator comparison, Yanyang’s emergency-site protocol, CQT, real-5G verification, and indoor spatial dotting.

What is a benchmark test?

A benchmark drive test is a controlled, route-by-route comparison of competing mobile networks. For this project, the same planned route and equivalent test conditions are used to compare MobiFone, Viettel, and VNPT/Vinaphone. The goal is to show relative coverage, data performance, stability, and voice quality—not merely to prove that one phone has service.

MobiFone

Project/customer network

Viettel

Benchmark competitor

VNPT / Vinaphone

Benchmark competitor

Test caseWhat it doesWhat to compareCompletion evidence
FTP DLTransfers data from the test server to the UE.Downlink throughput, stability, radio coverage/quality, and failures.Accepted PHU log for each required operator, RAT, and route.
FTP ULTransfers data from the UE to the test server.Uplink throughput, stability, radio coverage/quality, and failures.Accepted PHU log for each required operator, RAT, and route.
MOSRuns the planned VoLTE voice call and scores perceived speech quality.MOC/MTC accessibility, retainability, two-way audio, and UL/DL MOS.Accepted paired call logs with populated MOS results for each required operator and route.
Keep the route, direction, planned time window, test duration/file/server, and RAT configuration as equivalent as practical.
Label every phone and map the correct MobiFone, Viettel, or VNPT SIM to the correct PHU task before recording.
Keep each operator result separate. Record detours, congestion, device differences, invalid trials, and other conditions that affect fairness.
Compare accepted trials only; never use a truncated log, missing MOS value, wrong operator/RAT, or unrecorded deviation as a valid result.

Emergency-site test

This is an urgent validation of the assigned site or service condition, not a three-operator benchmark. Luo Yanyang’s current prepared protocol is the controlling document for the scope, sequence, thresholds, route/points, and deliverables.

  1. 1Get the current protocol directly from Yanyang or the assigned task owner. Confirm its version, site ID/name, location, deadline, and whether the site is new, restored, temporary, or under incident investigation.
  2. 2Confirm the on-air status, permitted test area, access contact, safety restrictions, baseline/post-change condition, and exact cells, bands, RATs, points, or route required by the protocol.
  3. 3Prepare only the required phones, SIMs, PHU tasks, locks, KML/floor plan, call pair, server/profile, and screenshots. Run a short proof test before travel or before entering the site.
  4. 4At the site, synchronize time and record the starting condition. Capture PHU BasicInfo and run idle, FTP, voice, speed, or handover cases only in the order and duration specified by the protocol.
  5. 5Record site/cell identity, LTE PCI/EARFCN, NR PCI/NR-ARFCN, radio KPIs, test result, exact time/location, abnormalities, access limits, and any deviation approved by the task owner.
  6. 6Validate the trace in PHU Assistant Lite, preserve the raw logs, upload to the instructed path, and report pass, fail, or inconclusive against the protocol. Notify Yanyang of missing scope or urgent failures.

CQT call cycle: MOC, MTC, and MOS

A CQT voice test needs both call directions and a working audio path. “Call connected” is not enough when the task also requires speech quality.

MOC · Mobile Originated Call

The test UE starts the call to the configured called number. Verify attempt, setup, alerting, connection, speech period, MOS result, and normal release.

MTC · Mobile Terminated Call

The test UE receives the call. Verify paging/ringing, answer or auto-answer, two-way audio, call retainability, MOS result, and release.

Bluetooth MOS connection

  1. 1.Identify the approved Bluetooth MOS headset/audio accessory for each MOC and MTC phone; do not swap labels between UEs.
  2. 2.Enable Bluetooth on the phone, place the MOS accessory in pairing mode, select its device name, and complete the PIN/confirmation prompt.
  3. 3.In the paired-device settings, enable Calls or Phone audio. Disconnect old headsets, watches, or car audio that may take the call audio route.
  4. 4.Place one short manual call. Confirm ringing, answer, microphone, and speech in both directions; verify the call screen shows Bluetooth audio.
  5. 5.Keep the project-defined volume/gain unchanged, disable mute, keep the microphone unobstructed, and prevent the accessory from sleeping.
  6. 6.Open the matching PHU MOS tasks only after both Bluetooth links are stable. If either device reconnects, repeat the audio proof call.

Run the paired PHU tasks

  1. 1.Confirm both SIMs have call credit, correct phone numbers, LTE service, IMS/VoLTE registration, and normal manual calling.
  2. 2.Assign one phone as MOC and the other as MTC. Check that the MOC called number matches the MTC SIM and that MTC answer/auto-answer follows the project script.
  3. 3.Start log recording on both phones. Arm the MTC side so it is ready, then start the MOC dialing task; follow the current PHU task order if it differs.
  4. 4.Watch for call attempt → alerting → connected → speech sample/MOS → normal release. Record setup failure, no answer, drop, one-way audio, or missing MOS as separate failures.
  5. 5.Verify both uplink and downlink MOS results are populated. A connected call with blank MOS is an incomplete MOS trial.
  6. 6.Repeat the required cycles and reverse MOC/MTC roles only when the test plan requires both directions. Keep the failed attempts in the evidence set.

PHU: verify whether 5G is actually connected

LTE PCI and EARFCN identify the LTE serving/anchor cell. They do not, by themselves, prove that the UE has an active NR connection.

PHU readoutInterpretationAction
LTE PCI + LTE EARFCN onlyLTE serving cell or NSA anchor is visible; NR is not yet proven.Start active traffic and check the NR/SCG fields.
LTE anchor + EN-DC/SCG connected + NR PCI + NR-ARFCN5G NSA is active.Capture LTE and NR radio KPIs during FTP/Speedtest.
Serving RAT = NR/5G SA + NR PCI + NR-ARFCN5G SA is active.Capture NR serving-cell and registration details.
5G icon, but no NR PCI/NR-ARFCN/NR measurements“False 5G” or NR not active at that moment.Do not report 5G as verified; generate traffic and retest.
  1. 1.Open PHU BasicInfo/Parameter view and record RAT, LTE PCI, EARFCN, band, RSRP, RSRQ, and SINR.
  2. 2.Compare the LTE PCI/EARFCN with the latest engineering parameters to confirm the expected anchor/serving cell.
  3. 3.Start FTP DL/UL or Ookla traffic because NSA NR may be added only when data demand begins.
  4. 4.Look for EN-DC/SCG/NR serving status plus NR PCI, NR-ARFCN, NR RSRP/RSRQ/SINR, and NR throughput contribution.
  5. 5.Take one BasicInfo screenshot before traffic and one while traffic is active; include time and indoor/outdoor position.
  6. 6.If LTE fields change unexpectedly or NR disappears, annotate the location and time for handover/cross-coverage analysis.

Channel naming: EARFCN is the LTE channel number. The 5G channel is NR-ARFCN. Record both for NSA; record NR-ARFCN and NR PCI for SA.

Indoor spatial dotting · manual dot trace

GPS is unreliable indoors. Spatial dotting anchors the PHU samples to the floor plan so Assistant Lite can replay the walk in the correct location.

1

Load the correct floor plan

Verify building, floor, orientation, scale, public/restricted boundary, and planned start/end points.

2

Select indoor/manual dotting

Use the project indoor map and begin one log for one floor and one clearly named test case.

3

Place the first dot

Stand at a recognizable landmark, tap the exact position on the floor plan, then start moving.

4

Dot every geometry change

Tap at every corner, corridor junction, entrance, escalator/elevator, direction change, and route deviation.

5

Walk steadily between dots

PHU distributes/interpolates samples along the segment; irregular speed or late dots distort the plotted location.

6

Handle pauses correctly

Add a dot at the actual pause/static test point and annotate the reason; do not let stationary samples appear along a moving segment.

7

Separate floors

Stop or segment the log before changing floors, load the next floor plan, and restart dotting from a confirmed landmark.

8

Verify before leaving

Replay the floor trace in PHU Assistant Lite and check that lines do not cut through walls, jump floors, or miss tested areas.

Indoor/outdoor 5G store test

Run the project-required 5G Speedtest at both positions, prove NR in PHU during active traffic, capture BasicInfo, speed, latency, server, time, and compare conditions before escalating an indoor gap.

Minimum evidence package

Spatial

KML/floor map, trace, direction, start/end time, deviations, public/restricted coverage.

Radio and service

Operator, RAT, band/lock, RSRP, SINR, PCI, throughput, latency, drops, MOS, BasicInfo.

Traceability

UE/SIM mapping, test-case name, raw log, screenshot, VUE trace ID, event notes, valid-trial marker.

05 · Benchmark control

Nine-route benchmark matrix

All nine routes remain incomplete: no MOS test was completed on routes 1–9. The recorded FTP work is shown below, but an FTP result alone does not close a route.

Completion rule: mark a route complete only after every required FTP UL/DL and MOS combination has an accepted log. Route 9 is incomplete, and Route 8 also has an outstanding FTP DL retest.
RouteDescriptionOverall statusOperational note
1MobiFone Office → Government OfficeIncompleteFTP UL/DL recorded; MOS was not tested.
2MobiFone Office → MPS Branch OfficeIncompleteFTP benchmark recorded; MOS was not tested.
3MobiFone Office → MPS HQIncompleteMOS was not tested. The handover also describes Route 3 as going to Government Office, so verify the latest route master.
4MPS Branch Office → MPS HQIncompleteFTP benchmark recorded; MOS was not tested.
5MPS Branch Office → Government OfficeIncompleteFTP benchmark recorded; MOS was not tested.
6MobiFone Office → Northern MobiFone Network CenterIncompleteSeparate FTP DL and UL runs were recorded; MOS was not tested.
7MPS HQ → Government OfficeIncompleteSeparate FTP DL and UL runs were recorded; MOS was not tested.
8MPS HQ → Vinhomes RiversideIncompleteFTP DL still requires retest and MOS was not tested.
9MPS HQ → National Data CenterIncompleteMOS was not tested, so this route is not complete. It is the longest route at about 2.5 hours; confirm the remaining scope and consider splitting the run.
06 · August 2026 lessons

Real cases and what they teach

Use these examples to recognize common failure patterns: false 5G, macro cross-coverage, interference, access constraints, incomplete reporting, and missing resource follow-up.

16 Aug

Noi Bai Airport T2 · Shop 1 / Shop 2 uplink

Shop 1 improved after optimization. Shop 2 remained below the >10 Mbps UL target. A nearby VNPT antenna was about 12–15 m horizontally from the referenced building floor; the team requested interference and load checks.

Intern takeaway

Do multiple static trials, preserve comparison points, and do not call the problem solved when one location improves.

13 & 19 Aug

MobiFone store · 21B Ba La

Indoor 5G was poor or absent while outdoor service was normal. One screenshot showed a 5G icon without a real NR connection.

Intern takeaway

Verify serving NR in BasicInfo. An icon is not proof of a 5G bearer. Compare indoor and outdoor under the same evidence package.

20 Aug

MobiFone store · 16 Dien Bien Phu

Indoor and outdoor 5G Speedtest plus FTP DL were collected at 21.0298, 105.8422 and combined with Ba La into one report.

Intern takeaway

Keep location identity and indoor/outdoor context clear when several stores share one deliverable.

25 Aug

Noi Bai Airport T1 · post-optimization walk test

Public areas on floors 1–3 were tested with 4G and 5G FTP DL. IBC improved, but some areas still handed over to macro. Restricted access had expired; Floor 3 public-area shape differed from the PPTX. 3G was not tested.

Intern takeaway

Report actual access and route coverage, state untested layers, and reconcile map mismatches before interpreting coverage.

26 Aug

VIP Cluster 21 · Riverside complaint

Immediate DT required a local MobiFone staff member because interns could not enter the VIP area.

Intern takeaway

Access is a test dependency. Coordinate through Phan Tuan Anh and never attempt unapproved entry.

27–28 Aug

VIP residential complaint report

The report showed poor 4G/5G coverage but initially lacked analysis and optimization suggestions. The suspected root cause was severe cross-coverage; post-DT optimization was pending and relocation/transmission work was needed first.

Intern takeaway

A customer report needs cause, evidence, proposed action, dependency, owner, and next verification—not screenshots alone.

07 · Communication and reporting

Make the result easy to scan and act on

The source notes use a fixed six-block email structure, an operator-by-RAT status table, explicit failure colors, and a report template aligned before customer output.

1

Greeting + overview

State whether this is a plan, result, or update. For plans: “This is just a plan (tentative) and may change.”

2

Change / precondition

Explain route, timing, access, SIM, vehicle, or scope changes before the table.

3

Test-plan/result table

Use No. · Route · Operator · RAT · Test case · Status · Remarks. Expand every route by operator and LTE/NR.

4

Reference images

Attach or CID-inline route maps, floor plans, BasicInfo, and screenshots with clear captions.

5

Vehicle / people / time

List driver, testers, field partner, start/end time, and access contact when relevant.

6

Notice + action + signature

State the one core request, owner, deadline, disclaimer, and fixed signature.

Result email pattern

Lead with the conclusion, then show the matrix

Subject: VIP 9 Road Benchmark Drive Test Result (29–31 Aug) – Viettel / MobiFone / Vinaphone

Opening: Please find below the benchmark drive test result for VIP 9 Road conducted from 29 to 31 Aug 2026, covering three operators: Viettel, MobiFone and Vinaphone.

Complete
Green ✓
Not tested
Red ✗
Incomplete
Reason in remarks

Action wording: Route 8 FTP DL could not be completed because the Viettel 4G and VNPT 4G SIM cards had insufficient balance. New SIM cards have been requested; arrange the retest when availability is confirmed.

Rule: The table carries the complete facts. The body carries the conclusion, risk, and one actionable request.

Report templates

  • Primary: Standard Template for VIP T1 Assurance_20260810 V1.pptx
  • Statistics reference: MBF RF Performance_20260808.pptx
  • Both front-line and GSC teams produce reports. Confirm the latest version before editing.
  • Customer output must include poor-area analysis and optimization suggestions.

Pre-send gate

  • Correct subject and recipients
  • Latest route and report template
  • Status colors match facts
  • Failure reason in remarks
  • Analysis and optimization
  • Owner and follow-up date
  • Images render in Outlook
  • Fixed signature and disclaimer
08 · Operational directory

Where work lives and who closes it

Use role-based escalation first, then confirm the current person and account in WeLink. Never assume a historical contact still owns the task.

DT Management

936714420879622473

Main coordination group for all drive-test activity.

10/08–16/08 Drive Test Record

997212977222389807

Noi Bai Airport T2 shop testing.

Hanoi Airport DT Assurance

994063112594419792

Airport T1 assurance and MobiFone store testing.

Approved log path

Group Space > DT Management > North > Benchmark DT Log > [date] > [location]Open the handover Onebox location
NameAccountRoleUse this contact for
Miao Peiqianm00907087RF Delivery LeaderDirect leader for DT tasks; interference, load, and RF follow-up.
Ouyang Changjuno60125604Delivery LeaderOverall delivery, VIP complaints, MobiFone coordination, and SIM purchase arrangement.
Hoang Minh Thaoh00708566Local MobiFone RFApproves DT plans and reviews reports before customer delivery.
Phan Tuan Anhp60120025Local engineerCoordinates MobiFone/VIP access and tracks cross-feeder updates.
Su Xiaobos00921749GSC engineerPerforms log analysis and report writing.
Nguyen Ha Phann50066043Local engineerField-testing partner.
Phan Truong Khangp50065883Local engineerField-testing partner.
Luo Yanyangl00947656RF engineerVIP complaint testing, Riverside DT support, and the project protocol to follow for emergency-site tests.

Open issue register · 27–28 Aug snapshot

ITC cross-feeder

64 issued · 40 resolved · historical counts do not fully reconcile; confirm current tracker.

14 pending

MobiFone-S cross-feeder

75 issued · 66 resolved.

9 pending

ITC hardware

93 issued · 36 resolved.

57 pending

MobiFone-S hardware

51 issued · 27 resolved.

24 pending

The handover totals 104 pending items. Phan Tuan Anh supplied ongoing updates.

Outstanding handover actions

CQT report retest

Installation-quality issues require a retest.

Not done

VIP residential analysis

Add optimization suggestions and address relocation/transmission dependencies.

Needs action

Shop 2 uplink

Interference and load check requested; target was >10 Mbps.

Low UL persists
View benchmark route gaps

Fast escalation map

VIP access

Phan Tuan Anh · send access documents only through approved channels.

Site on-air check

Nguyen Trong Giap · 00079600; also check [War Room] MBF 5G project – Ha Noi cutover.

More SIMs

Ouyang Changjun coordinates with Dang Hong Quan / Thai Huu Tuan Ha.

Interference / load

Miao Peiqian for RF checks; Su Xiaobo for log analysis.

09 · Original handover files

Download the working references

Use the live team workspace as the operational source of truth. These files are the dated references used to build this guide.

Before you leave for the field

If the route, SIM, access, logger, and owner are not confirmed, the test is not ready.

Scope confirmedSIM provenAccess approvedRoute openedLogger validatedUpload owner named